A headline number usually belongs to one of four categories. We label every project with which one, because “$X billion is coming” means something very different in each:
Meta AI data centre
Sturgeon County, north of EdmontonGround broken. This is the one that is genuinely real and building, and it is also one of only two projects holding a share of the grid's interim large-load allocation. More than 3,000 construction workers at peak, and, by Meta and the province's own figures, just over 300 permanent jobs.
Source: Meta groundbreaking announcement
Wonder Valley AI Data Centre Park
Greenview Industrial Gateway, near Grande PrairiePitched as potentially the world's largest AI data centre park, and planned to run off-grid on natural gas plus geothermal, which is one way around the grid bottleneck. Still an early-stage vision, not a build.
Source: Alberta Major Projects registry
Four announced facilities (Olds, Bonnyville, Calgary, Edmonton)
Four sites across AlbertaAnnounced with budgets stated, but no shovels yet. A useful reminder that most of the numbers in the news are plans, not construction.
Source: Alberta Major Projects registry
Synapse data centre (Olds)
Near OldsThe Alberta Utilities Commission rejected the on-site power plant twice: first in March 2026 on procedural and evidentiary grounds, then again in August 2026. The company has filed again. This is the part of the story that rarely makes the news: not every announcement gets approved.
Source: The Narwhal
Rocky View County campus
Rocky View CountyCounty councillors voted it down 6 to 1 in September 2025 after residents organized against it. Community opposition and zoning now matter to whether these projects happen almost as much as power does.
Source: Maclean's
This tracker is a work in progress. Every figure here traces to a named source, and we are still confirming a few against the original filings. We will add projects, correct mistakes, and note changes as they happen. Know of one we are missing, or a stage that has moved? Tell us.