Where it stands
The facts
What we know about Meta
What it is
Meta's first Canadian data centre, in Sturgeon County north of Edmonton. Meta puts the investment at more than CA$13 billion and the facility at about one gigawatt. Ground has been broken, which makes it the clearest example on this site of a project that is real and building rather than announced.
Why it matters for the grid
It is one of exactly two projects holding a piece of the grid operator's 1,200 MW interim large-load allocation through 2028. In other words, it is not just permitted, it has a connection — which most of the queue does not.
The jobs, attributed
Meta and the Government of Alberta say the project means more than 3,000 construction workers at peak, more than 300 permanent jobs, and about $250 million a year in government revenue. Those figures come from the company and the province, and we report them as theirs, not as independently verified.
Source: Meta groundbreaking announcement. Full list on Citations.
What the community is saying
The coverage and the response
Real reporting and documented community response, cited. We link out so you can read the source yourself, not our summary of it.
Who benefits: AI data centres in Alberta
The province lays out its case: more than 3,000 construction jobs, 300+ permanent, and about $250M a year in revenue. Its own figures.
Government of Alberta →
NewsBreaking ground on Meta's first data centre in Canada
The company's own announcement of the Sturgeon County build, the one genuinely funded and under construction.
Meta →
NewsAlbertans raise water, noise and farmland concerns at town halls
The same worries residents brought to provincial sessions apply to the projects near their communities.
CBC News →