Synapse data centre

Near Olds

Rejected
BackerSynapse Data Centre Inc.
SizeLarge-scale, with its own gas power plant
Investment~CA$10 billion
StatusRejected
Rejected / stalled

What we know about Synapse

What it is

A large proposed data centre near Olds, reported at around CA$10 billion, that depended on building its own on-site natural gas power plant to sidestep the grid.

Why it is here

The Alberta Utilities Commission rejected that power plant — first in early 2026 on procedural and evidentiary grounds, and again later in the year. The company has continued to file. This is the category almost nobody covers: a headline-grabbing announcement that the regulator turned down.

Our reading

The lesson

For projects that plan to bring their own generation, the generation approval is often where the project lives or dies — not the data centre itself.

Source: The Narwhal. Full list on Citations.